Project Schedule
Out To Bid                                                      January 23
Mandatory Pre-Bid Conference                     TBD
Filed Subcontractor Bid Opening                   Tues, February 20 at 2 pm
General Contractor Bid Opening                    Tues, February 27 at 2 pm

Bid Location: Bureau of General Services, 4th Floor, Cross Building, Augusta

Construction will begin as soon as the ground thaws in the spring 2018.

Anticipated completion of the entire project, renovation and new construction is May, 2020.

There is 21,560 gross square feet of new construction and 4,950 square feet of renovation in this state funded project.

Estimate of state’s project cost is $14 million.

County cost for real estate purchases, after state reimbursement, is $477,000.

Four parcels w/ houses were purchased in 2017, w/ continued tenancy in two. Anticipated cost of county-funded peripheral improvements over next two years is $250,000. Cost to county for last year’s full rehabilitation of the main building exterior was $555,000.